Surat Metro Phase 1 2026: 40.35 Km Network, 38 Stations and Progress

The Surat Metro Phase 1 project, executed by the Gujarat Metro Rail Corporation, has reached several important technical milestones in 2026. The project covers a total network length of 40.35 km with 38 stations. This metro system is expected to transform daily commuting in Surat by connecting major industrial, diamond and residential hubs across the city. The complete operational rollout is targeted for December 2027, while a priority stretch is moving toward commercial clearance. The project has seen steady progress through 2026 with trial runs, tunnelling breakthroughs, bridge completion and station construction all moving forward. For the people of Surat, the metro will offer a faster, safer and more reliable way to travel across the city once it becomes fully operational.

Surat Metro Phase 1 Network and Corridors

The system consists of two primary intersecting lines connecting major industrial, diamond and residential hubs.

CorridorTerminalsTotal LengthStationsLayout
Red Line (Corridor 1)Sarthana to DREAM City21.61 km20Elevated plus 6.47 km underground
Green Line (Corridor 2)Bhesan to Saroli18.74 km18Fully elevated

Together, the two corridors cover 40.35 km and 38 stations. The Red Line includes a significant underground section of 6.47 km, while the rest of the network is elevated. This mix of elevated and underground sections allows the metro to pass through densely built areas while maintaining efficient travel speeds on open stretches.

Surat Metro Priority Stretch Trial Runs

In April 2026, GMRC launched a 500 hour testing and trial phase on an 8.5 kilometre priority corridor between Dream City and Althan Tenement. The testing evaluates:

  • Speed parameters
  • Emergency braking systems
  • Overall technical integration

The testing is being carried out to obtain Commissioner of Metro Railway Safety approval. This approval is an important step before passenger services can begin on the priority stretch. The trial runs help engineers confirm that the trains, tracks and signalling systems are working together correctly and meet the required safety standards.

Final Underground Breakthrough at Surat Railway Station

A major underground tunnelling milestone was achieved on September 25, 2026. Tunnel Boring Machine Tapi achieved its final breakthrough at the Surat Railway Station. This completed the complex underground tunnelling package connecting Kapodra to the main railway hub. The breakthrough marks the end of one of the most technically challenging parts of the project because tunnelling through a busy urban area near the railway station requires careful planning and execution. With this milestone complete, the project moves closer to connecting the underground section with the rest of the metro network.

Tapi River Bridge Completion

Another major construction milestone was achieved in January 2026. Civil construction completed the critical structural span work across the Tapi River, physically linking Athwalines and Adajan for the Textile Corridor. This bridge is an important link because it connects two major parts of the city that were previously separated by the river. The completion of this structural work allows further construction to proceed on the metro line that crosses the river, bringing the project closer to its overall completion target.

Station Construction Progress

Several Surat Metro stations are progressing through advanced structural stages. Stations such as Althan Tenement and Roopali Canal are in advanced structural phases. Painting, entry and exit structures, and concourse level integration are progressing, while roofing and lift installation are also moving ahead. These stations will form the backbone of the metro network, providing passengers with access points across the city. As the station construction moves forward, the project is taking visible shape on the ground, and residents can see the metro infrastructure coming together.

Surat Metro Extension to High Speed Rail Station

On September 30, 2026, GMRC floated a ₹356.54 crore tender for a 4.4 km elevated extension from Saroli to the upcoming Surat High Speed Rail Station. The extension is planned to allow future high speed bullet train passengers to switch to the Surat Metro network. This extension is an important step because it will connect the metro with the high speed rail corridor, making it easier for passengers to transfer between the two systems. Once complete, the extension will help integrate the metro with the wider rail network and support the growth of public transport in the region.

Surat Railway Station Multi Modal Transport Hub

The Surat Railway Station is undergoing redevelopment into a Multi Modal Transport Hub. The project is slated for completion by December 2026. It is planned to connect the Metro lines with the Indian Railways network, city buses and the BRTS. This integration will allow passengers to move between different modes of transport without leaving the station complex, making travel more convenient and efficient. The hub will bring together multiple transport systems in one location, which is expected to reduce travel time and improve the overall commuting experience for people in Surat.

Metro Operation Control Centres

Two train maintenance depots are under active development at Dream City and Bhesan. These facilities are being developed to manage fleet operations. The depots will be responsible for maintaining the metro trains, ensuring they remain in good working condition and are ready for daily service. The control centres at these depots will help manage train schedules, monitor operations and respond to any technical issues that may arise during daily operations.

Surat Metro train on elevated tracks, with city skyline and busy roads below.
Surat Metro is developing connections with the railway network and other city transport systems (representative image).

Surat Metro Job Creation

The project has also moved toward live operations with recruitment activity. GMRC opened recruitment notifications for 383 non executive positions. These positions include:

  • Station Controllers
  • Train Operators
  • Maintainers

These recruitments are a sign that the project is preparing for the operational phase. As the metro network gets closer to completion, more jobs are expected to be created in operations, maintenance and administration. This is good news for job seekers in Surat and the surrounding areas who are looking for opportunities in the public transport sector.

Surat Metro Phase 1: Key 2026 Milestones

The major developments mentioned for 2026 include:

  • April 2026: 500 hour priority stretch testing started between Dream City and Althan Tenement
  • January 2026: Critical Tapi River bridge structural span work completed
  • September 25, 2026: TBM Tapi achieved its final underground breakthrough at Surat Railway Station
  • Q3 2026: Althan Tenement and Roopali Canal stations reached advanced structural stages
  • September 30, 2026: ₹356.54 crore tender floated for the 4.4 km Saroli to Surat HSR Station elevated extension
  • December 2026: Surat Railway Station Multi Modal Transport Hub is slated for completion
  • December 2027: Complete Surat Metro Phase 1 operational rollout is targeted

Conclusion

The Surat Metro Phase 1 project covers 40.35 km with 38 stations across the Red and Green corridors. During 2026, the project recorded important developments including priority stretch testing, the final underground breakthrough at Surat Railway Station, Tapi River bridge completion, station construction progress and the proposed extension toward the Surat High Speed Rail Station. The complete operational rollout of the Surat Metro Phase 1 network is targeted for December 2027. Once operational, the metro is expected to improve connectivity across Surat, reduce travel time for daily commuters and support the city growth as a major urban centre in Gujarat.

Frequently Asked Questions

Q1. What is the total network length of Surat Metro Phase 1?
A1. Surat Metro Phase 1 covers a total network length of 40.35 km with 38 stations across two corridors.

Q2. How many corridors are there in Surat Metro Phase 1?
A2. There are two corridors. The Red Line runs from Sarthana to DREAM City covering 21.61 km with 20 stations, and the Green Line runs from Bhesan to Saroli covering 18.74 km with 18 stations.

Q3. When did the trial runs start on the Surat Metro priority stretch?
A3. The 500 hour testing and trial phase on the 8.5 km priority corridor between Dream City and Althan Tenement started in April 2026.

Q4. When is the full Surat Metro Phase 1 expected to be operational?
A4. The complete operational rollout of Surat Metro Phase 1 is targeted for December 2027.

Q5. What is the Surat Railway Station Multi Modal Transport Hub?
A5. The Surat Railway Station is being redeveloped into a Multi Modal Transport Hub, slated for completion by December 2026, connecting the Metro lines with Indian Railways, city buses and BRTS.